Uhlmann Road, Burpengary boat ramp upgrade

Construction commenced in July 2019, to upgrade the boat ramp at Uhlmann Road, Burpengary, on the southern bank of the Caboolture River. This prime location provides direct access to Moreton Bay from the mouth of the river.

Completed in October 2019, the upgraded facility now features a wider ramp with an extra lane and a new floating walkway.

The installation of the floating walkway on the downstream side has the added benefit of providing some shelter from wave action coming up from the river mouth.

Stanage Bay boat launching facility upgrade

Stanage Bay's public boat ramp accesses the pristine waters around Broad Sound, Shoalwater Bay, Percy Isles, Duke Island, and Thirsty Sound.

The upgrade was completed in October 2019 and the facility now features a widened boat ramp with two, four metre wide lanes, a new 2.5 metre wide floating walkway, and a new breakwater to provide protection from wave action.

Riedel Road, Carbrook new boat ramp

On-site works commenced in March 2020 to construct a new public boat launching facility at Riedel Road, Carbrook.

Completed in late-June 2020, the new two-lane boat ramp with floating walkway is located on the northern bank of the Logan River.

Mission Beach Clump Point boating facility

Construction on the Mission Beach Clump Point boating facility project continues. This project was divided into two elements:

  • civil works for an additional boat ramp lane, car park expansion, and large new detached breakwater were completed in April 2020.
  • in-water works behind the breakwater for an access jetty, two floating walkways, two berthing pontoons, six pen berths, and five swing moorings. Works commenced in March 2020 with completion planned for late-2020.